Whole-Site EICR in a Single Weekend

The Task

A national organisation’s headquarters in Hampshire needed a full EICR covering both its critical and non-critical circuits. The only access available was a single weekend.

The Outcome

After a pre-start survey, our team was on site from 6pm on the Friday, working through the weekend with overnight accommodation arranged locally.

The scope covered around 800 non-critical circuits across 24 distribution boards, three control panels and 30 MCCBs. It also covered the cables leaving the critical switch panels and distribution boards.

The programme was built so that both the critical and non-critical testing fitted inside the one weekend, giving the client a full picture of the site’s installation.