Phased Electrical Programme at a Historic Country Estate

The Task

Following our EICR of the main house, a historic country estate in Buckinghamshire asked us to put right the defects found and improve the electrical infrastructure. The work covered the main house, gardens, greenhouses and estate buildings.

The Outcome

We split the work into a phased programme over three years, so the estate could plan and budget each stage. Potentially dangerous (C2) items were dealt with first, followed by switchboard and infrastructure improvements.

Much of the house is wired in original mineral-insulated (MICC) cable. Where possible we re-terminated and extended it rather than ripping it out, which protected the historic fabric of the building. Each phase was tested and certified on completion.